_______________________
Client name: Equinor
Project type: Upgrade of pipe insulation
Location: Onshore Norway
Scope: 5 300 LM
_______________________
The Challenge
- Installation of the insulation is very time consuming due the complex shape and lack of space. Client wants a solution that is easy to install, in order to reduce man ours on site.
- Reduce the risk of CUI
- Improve HSE
The Solution
- Prefabricated GRP cladding with Oryza-650 aerogel insulation(All-in-One)
- All fittings and complex part supplied prefabricated to site
- Rubber End Caps to terminate the insulation/cladding
The Benefits
- Easy to install, also for inexperienced workers
- Up to 60% reduction of man hours on site
- Very good CUI peformance
- The amount of dust releast from aerogel during installation is significantly reduced
Conclusion
By using the prefabricated system Benarx® All-in-One a significant part of the work is moved from site to the controlled environment of a prefabrication facility. This ensure a uniform quality of all the supplied parts and a easy installation on site reducing the risk for CUI.